Follow up email from the data center. Hopefully we have seen the last of the power issues.
Quote:
We take full responsibility for the events that occurred today.
Unfortunately episodes like today's blown power cable are almost
impossible to forecast. That said, we are still moving forward on
our extensive diagnostic power test on Monday, June 25th at 7:00pm
EDT, as previously communicated. Once again, we do not expect any
disruption of service during this test.
We apologize for the interruption of service that occurred today and
we thank you for your continued patience.
|
.